Escalation Factors for ID PFH 80-1(1), Fernan Lake Road

Latest Month: August 2008
Fuel Price: 3.68
Asphalt Price: 825.00

Computation of Contract Base Price Indexes
Asphalt Cement Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average for prices in the four "Asphalt Weekly Monitor ®" publications immediately preceding the bid opening.
Week EndingAsphalt  ($/metric ton)
June 27625.00
July 4650.00
July 11737.50
July 18737.50
Base Price Index687.50

Fuel Price Adjustment
The Base Price Index (BPI) is a price index determined by arithmetic average of OPIS publications daily rack prices for the 28 calendar days preceding the bid opening.
Week EndingFuel  ($/gallon)
June 273.88
July 44.04
July 114.09
July 184.18
Base Price Index4.05


Archived Months for 2008
MonthFuelAsphalt
July4.08718.75

   


Home | About WFLHD | Projects | Procurement | Design Resources | Contact Information

USDOT | FHWA | FLHP | EFLHD | CFLHD | WFLHD

Please send your questions or comments to webmaster@mail.wfl.fhwa.dot.gov
Last update: September 12, 2008