Project Schedule
The proposed schedule for the project is as follows:
Public Involvement:
Ongoing through project
Notice of Intent to Prepare an EIS:
Completed
Scoping Process:
Completed
Draft EIS:
Completed. May 24, 2004
Agency/Public Review and Comment:
Completed
Public Meeting:
Completed. June 24, 2004
Final EIS:
Completed. April, 2005
Record of Decision (ROD):
Completed. July, 2005
Final Design Completion:
2005 - 2007
Construction:
2008 - 2009