Update for February 24, 2010

For the week of March 1st to March 5th the Contractor will be working days and nights. Day work consists of finishing installing micropiles, along with forming and placing rebar for the grade beam at Wall 6. Also, continued subgrade work, “pecking” rock slopes, and possible utility vault and/or drop inlet installations time permitting. Night work will consist of hauling stockpiled waste material from the Lake Creek Bridge area back to the waste area across from the Riggins Rodeo Grounds.

The Contractor plans on working nights (Monday, Tuesday, Wednesday, and Thursday) this week. Be aware of the road construction opening / closure schedule for night work.

Be aware of the road opening / closure times in the schedule for the remainder of February through March 5th.

For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs and temporary traffic signals placed for your safety, and everyone else’s safety also.

Here is a glance at the week of March 1st through March 5th showing the schedule for road openings / closures:

Construction Schedule
Construction Schedule

 

Construction Photo
“Pecking” away at rock slope above Island Bar

Construction Photo
Setting forms for the grade beam at Wall 6

Inspirational Quote: In just two days, tomorrow will be yesterday.

Click on the site below for information on the “Women with Bait Steelhead Derby” held all of February through the first weekend in March.
http://www.rigginsidaho.com/women_with_bait.htm

Gary Wrightman
Project Engineer
Western Federal Lands Highway Division
Federal Highway Administration

If you would like to provide a comment, click here: salmonriver@dot.gov