Update for March 25, 2010

For the week of March 29th to April 2nd the Contractor will be working days and nights. Day work forming and placing rebar for Wall 6 along with a concrete pour. Also, continued subgrade work, “pecking” rock slopes, and possible utility vault and/or drop inlet installations time permitting. Night work will consist of hauling stockpiled waste material to the waste area across from the Riggins Rodeo Grounds, “pecking” away at rock slopes, and various other project related work as time permits.

The Contractor plans on working nights (Monday, Tuesday, Wednesday, and Thursday) this week. Be aware of the road construction opening / closure schedule for night work.

For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs and temporary traffic signals placed for your safety, and everyone else’s safety also.

Here is a glance at the week of March 29th through April 2nd showing the schedule for road openings / closures:

Construction Schedule
Construction Schedule
Construction Schedule

 

Construction Photo
Working subgrade at Wall 13

Construction Photo
Pouring concrete into a section of the grade beam at Wall 6

Humorous Poster

Gary Wrightman
Project Engineer
Western Federal Lands Highway Division