Update for September 1, 2010
The Contractor will be performing various construction activities throughout the project during the week of September 6th through September 10th. This could be drilling within the Wall 8 / 9 location and/or possible other construction related activities.
NOTE: Over Labor Day weekend, that portion of the Salmon River Road under construction will be open to public traffic from 6:00am Thursday, September 2nd, through 4:00pm Tuesday, September 7th.
For those of you planning on visiting the area to camp, hunt, fish, and/or just to enjoy the area, the Salmon River Road may have changed since your last visit, so please be cautious and patient when traveling through the construction area and abide by the signs and temporary traffic signals placed for your safety, and everyone else’s safety also.
Here is a glance at the week of September 6th through September 10th showing the schedule for road openings / closures:


Night drilling of soil nails high on slope at Wall 8 / 9
Quote of the week
“Success is dependent on effort.”
~ By Sophocles ~
Gary Wrightman
Project Engineer
Western Federal Lands Highway Division